Affordability was a primary factor when making the concrete forming product selection for the construction of the Pacifica Apartments in Tacoma, Washington. The two-building, 230,000-square-foot apartment complex featured 177 units, two underground parking garages, and required 7,000 yards of structural concrete – including five post-tensioned reinforced concrete decks with up to 800 cubic yards of concrete in each.
Rush Commercial selected 3/4-inch MDO (Medium Density Overlay) plywood for the concrete formwork. Key considerations were cost-effectiveness and how easily the panels could be to cut to size for use as fill-in formwork.
There were many steps in the wall elevations and many different column block-outs on the exterior walls. Wood panels were the most cost effective for the formwork because they could cut and modify the panels to fit as needed. Then, after the concrete was poured, they cut and modified the panels again to use in others areas.